Tärnsjö tannery have under a longer time been planning to move some of the concrete pillars in
their building, at the same time the conditions to broaden an existing gateway and make a
building plan for a corroded roof is investigated. Current construction plans can´t be found and
that severely complicates the work.
Moving the pillars will result in higher stress on the current beam and measures have to be taken
to retain the buildings stability. An iron beam or reinforcement with carbonfibre will manage the
stress. The gateway can easily be widened if an ironbeam is laid as reinforcement at the top of the
gate. And parts of the lower windows need to be cast shut. Because of the missing construction
plans the beam over the gate is projected to carry all of the loads in the wall, including the weight
of the joists. The reason why the ceiling in the warehouse has begun corroding depends to big part
on the tarpaper that should protect the ceiling from damp, it´s old and needs to be changed. The
ceiling has become an outdoor room which means increased tear on the current tarpaper. To solve
this problem the ceiling needs to be cleaned and the paper replaced.